Solution:
- Consolidated brands and parts to dramatically simplify procurement and reduce equipment costs
- Transitioned inventory from client to Crane ownership
- Central warehouse for 5 plants, including mechanical seal repair
- Quick response service standards and support, including one hour turnaround and blanket PO's
- Established process to better optimize inventory based on actual usage
- Power End Replacement program
|
Results:
- Removed $1.1 million from client inventory
- Power End Replacement Program
- Save $300,000/year in labor costs
- Improved MTBF
- Transactional Savings
- Bi-monthly Invoicing
- Store Room Receiving Eliminated
- PO Issuance Reduced
|